The new Csenar residence in Crystal Lake, IL.

 

05/20/2000

The foundation is poured and the wooden base is mounted.  They dug the hole on 4/28, but heavy rain all through May slowed the progress down considerably.  The house next door is two weeks ahead of ours, so we pretty well know where we should be at all times during construction.

05202000.jpg

 

05/28/2000

The frame is going up.

 05282000.jpg

 

06/04/2000

Within two days of this picture, the entire house is framed, roof and all.

06042000.jpg

 

06/11/2000

The shingles are going on.  Not much is happening on the inside..

06112000.jpg

 

06/17/2000

The roof is on and the windows are going in.  Conduit and pipe and ducts are going inside..

06172000.jpg

 

06/25/2000

The garage doors are on.

06252000.jpg

 

07/08/2000

The brick facade and aluminum siding are going on.  A lot of topsoil has already been spread in the back..

07082000.jpg

 

11/01/2000

The house has been finished for a while and landscaping is in the front and both sides.

11012000-1.jpg

 

11/01/2000

Another view with the landscaping.

11012000-2.jpg