05/20/2000
The foundation is poured and the wooden base is mounted. They dug the hole on 4/28, but heavy rain all through May slowed the progress down considerably. The house next door is two weeks ahead of ours, so we pretty well know where we should be at all times during construction.
05/28/2000
The frame is going up.
06/04/2000
Within two days of this picture, the entire house is framed, roof and all.
06/11/2000
The shingles are going on. Not much is happening on the inside..
06/17/2000
The roof is on and the windows are going in. Conduit and pipe and ducts are going inside..
06/25/2000
The garage doors are on.
07/08/2000
The brick facade and aluminum siding are going on. A lot of topsoil has already been spread in the back..
11/01/2000
The house has been finished for a while and landscaping is in the front and both sides.
11/01/2000
Another view with the landscaping.